Acacia Maden SPP
#1078of 1935 in Renewable energy#17of 75 in TR#33of 154 in Intl. Carbon Registry (ICR)#844of 1287 in ACM0002
Audit Analysis
Acacia Maden SPP is a grid-connected renewable energy project in Turkey (ACM0002 v22.0) with a jurisdictional baseline and a 10-year crediting period. The project shows no material findings, no reversal events, and a conservative claimed ERR well below the pro-rata lifetime expectation, but significant gaps in VVB identification, MRV parameter disclosure, and permanence safeguards limit confidence in the overall quality of the credit.
Red Flags
- VVB name and additionality verification status are not stated in any available document, leaving the combined additionality test unconfirmed by an independent body
- Total ERR verified figure is absent from the extracted record, so the claimed 24,658 tCO2e cannot be independently cross-checked against a verified value
- CORSIA eligibility and CCP status are both unstated, creating uncertainty about dual-channel or double-claiming risk
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2025 | 55,570 | 0 | 55,570 | |
| 2026 | 66,284 | 0 | 66,284 | |
| 2027 | 66,284 | 0 | 66,284 | |
| 2028 | 66,284 | 0 | 66,284 | |
| 2029 | 66,284 | 0 | 66,284 | |
| 2030 | 66,284 | 0 | 66,284 | |
| 2031 | 66,284 | 0 | 66,284 | |
| 2032 | 66,284 | 0 | 66,284 | |
| 2033 | 66,284 | 0 | 66,284 | |
| 2034 | 66,284 | 0 | 66,284 | |
| 2035 | 10,714 | 0 | 10,714 | |
| Total | 662,840 | 0 | 662,840 |
Risk Indicators
Combined test referenced but VVB verification unconfirmed
no reversals reported
0% deduction, deemed negligible — reasonable for grid-connected RE
Jurisdictional baseline with 2022 grid EF; reassessment date not stated
FPIC conducted, grievance mechanism present, safeguards documented
CORSIA and CCP status both unstated — dual-channel risk unassessed
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →