Anhua Bundled Small Hydropower Project
#1347of 1935 in Renewable energy#815of 1084 in China#1070of 1459 in CDM (UNFCCC)#434of 806 in AMS-I.D
Audit Analysis
A CDM small-hydropower bundle in China with a solid investment-test additionality assessment verified by DNV, but the project's integrity is undermined by a severe over-claim in the original PDD (ERR reduced by roughly 86% after corrective actions removed the Shankou sub-project) and a grid-emission-factor discrepancy between the validation report and an appendix. No monitoring or verification data is available in the extracted record, leaving the actual delivery of credits unverified.
Red Flags
- Original PDD claimed 149,720 tCO2e/yr; after CAR 4 removed the Shankou project the validated figure dropped to 21,389 tCO2e/yr — an 86% reduction indicating the initial bundle was substantially over-credited
- Grid emission factor contradiction: validation report uses 0.85285 (2009) while an appendix cites 1.1255; the higher value would inflate claimed reductions by ~32%
- Four corrective actions were required at validation, including missing PLF calculation, unjustified auxiliary power losses, and an IRR benchmark breach for one sub-project
- No monitoring or verification reports are present in the extracted record; actual credit delivery over the 2011–2018 crediting period is unverified
- Minimum extraction confidence is rated low, meaning at least one key document was poorly readable
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
Investment test, VVB-verified (DNV)
Avoidance project; no reversal risk for grid-connected hydro
0% deemed negligible; reasonable for grid-connected hydro
Jurisdictional grid EF (2009); EF discrepancy in appendix; n
Safeguards mentioned and benefit sharing described; no FPIC
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →