Baoshan Supahe Chaoyang Hydropower Station
#1408of 1935 in Renewable energy#864of 1084 in China#1141of 1459 in CDM (UNFCCC)#1080of 1287 in ACM0002
Audit Analysis
A CDM hydropower project in China with a jurisdictional baseline and investment-test additionality, but the available record is limited to the validation report and PDD with no monitoring data, no buffer pool information, and low extraction confidence. Four material findings (CARs) were raised during validation, and two contradictions between documents reduce confidence in the data. The project is moderate in quality but lacks the depth of evidence needed for a high-confidence assessment.
Red Flags
- No buffer pool or permanence mechanism is stated in any available document, leaving reversal risk unaddressed for a 7-year crediting period
- No monitoring reports or verified ERR figures are available; the 554,218 tCO2e figure is an ex-ante claim with no verified counterpart
- Low extraction confidence across the document set, with one source document listed as 'unknown'
- Four material findings (CARs) were raised during validation, including a missing parameter in the PDD and outdated grid emission factor
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2010 | 78,972 | 0 | 78,972 | |
| 2011 | 128,397 | 0 | 128,397 | |
| 2012 | 86,800 | 0 | 86,800 | |
| 2013 | 43,251 | 0 | 43,251 | |
| Total | 337,420 | 0 | 337,420 |
Risk Indicators
Investment test present; VVB confirmation not verified in ex
no reversal e
0% deduction, 'deemed negligible' — reasonable for hydro but
Jurisdictional baseline, grid EF 0.497575 (2015), reassessed
Safeguards and benefit sharing mentioned; FPIC and grievance
CORSIA and CCP status both not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →