5.9/ 10
Integrity
6.3
Transparency
5.5
Claim Safety
6.5
Documentation
4.8

Audit Analysis

The Belen Wind Power Plant is a Gold Standard wind project in Turkey with a VVB-confirmed investment additionality test and a jurisdictional grid-emission-factor baseline reassessed in 2024. The claimed and verified emission reductions match exactly at 62,436 tCO₂e for the first monitoring period, and safeguards (FPIC, grievance mechanism, benefit sharing) are documented. However, the leakage justification is marked as not addressed, reversal events are not explicitly discussed, the extraction confidence is low, and 15 corrective action requests were raised during verification (all resolved), indicating meaningful documentation quality issues.

Red Flags

  • Leakage deduction of 0% with justification recorded as 'not addressed' in the 2025 verification report, while an earlier 2021 report described it as 'quantified' — the more recent document is privileged but the gap in explicit justification remains
  • 15 Corrective Action Requests and 6 Clarification Requests were issued during verification (all closed), including errors in baseline emission calculation, net electricity generation values, and project start date — indicating significant MRV documentation weaknesses
  • Minimum extraction confidence is rated low, meaning at least one key document was poorly readable, reducing reliability of the extracted data
  • Reversal events are recorded as 'not addressed' in the 2025 verification report, though wind is an avoidance project with inherently low reversal risk
  • One Forward Action Request remains open and must be checked at the next verification

Credit Vintages

IssuedRetiredAvailable
2009
7,3737,3730
2010
46,79746,7970
2011
50,75950,7590
2012
62,73662,7360
2013
81,26581,2650
2014
84,36084,3600
2015
80,76180,7610
2016
66,68066,413267
2017
19,12419,1240
2018
71,82754,32717,500
2019
70,10370,1030
2020
72,36061,75510,605
2021
68,63362,2056,428
2022
66,89127,15439,737
2023
7,05007,050
Total856,719775,13281,587

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Avoidance project, low reversal risk

Leakage

0% deduction, justification not addressed

Baseline

Jurisdictional grid-EF, reassessed 2024

Safeguards

FPIC, grievance mechanism, benefit sharing documented

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-01ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents