Biomass based Co-generation plant at Birlagram, Nagda, Madhya Pradesh, India.

CDM-6401 ↗

#71of 352 in Biomass#467of 975 in India#654of 1459 in CDM (UNFCCC)#24of 115 in AMS-I.C

5.2/ 10
Integrity
5.5
Transparency
4.5
Claim Safety
5.0
Documentation
6.0

Audit Analysis

A CDM biomass co-generation project with confirmed additionality and justified negligible leakage, but significantly under-delivered (49.4% below ex-ante estimate) due to operational shortfalls, and generated 32 corrective action requests during verification. The project-specific baseline and several unaddressed sustainability indicators (feedstock, carbon content) limit confidence in the overall credit quality.

Red Flags

  • Actual emission reductions were 49.4% lower than the ex-ante estimate due to fewer operational days and unexpected outages, indicating the original projection was overly optimistic
  • 32 Corrective Action Requests and 13 Clarification Requests were raised during verification, suggesting significant quality-control issues in the project documentation
  • A numerical discrepancy exists between the PDD (97,404 tCO2e) and the monitoring report (454,319 tCO2e) for the total ERR claimed figure, creating ambiguity about the true credit volume
  • Feedstock sustainability and carbon content testing are not documented in any available record

Credit Vintages

IssuedRetiredAvailable
2023
539,8810539,881
Total539,8810539,881

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Avoidance project, no storage risk

Leakage

Negligible with stated justification

Baseline

Project-specific, 2009 grid EF

Safeguards

Mentioned but FPIC/grievance not detailed

Double-claim

CORSIA/CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-26AMS-IC

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents