Biomass based Cogeneration unit at Co-operative Sugar mills in Nakodar, Punjab, India
#155of 352 in Biomass#725of 975 in India#1077of 1459 in CDM (UNFCCC)#50of 115 in AMS-I.C
Audit Analysis
A CDM biomass cogeneration project with VVB-confirmed additionality but significant data gaps and a baseline-method contradiction between the PDD and validation report. The 14 corrective action requests during validation raise concerns about the robustness of the underlying data, and the absence of any monitoring or verified-credit figures limits the ability to assess actual delivery against claims.
Red Flags
- Baseline method contradicts between the PDD (jurisdictional) and the validation report (project-specific); the project-specific baseline is less robust and the discrepancy undermines confidence in the baseline calculation
- 14 Corrective Action Requests were raised and closed during validation, indicating substantial data-quality issues that had to be remediated before the project could be validated
- No monitoring period, verified ERR, or usage-rate data is available in the extracted record, making it impossible to confirm whether the 706,840 tCO2e lifetime claim was actually delivered
- Low extraction confidence across the document set means key figures may be missing or misread
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed investment test
Avoidance project, no reversal risk
0% deduction, 'deemed negligible' only
Project-specific; PDD/VR contradiction
Mentioned; no FPIC or grievance detail
CDM project; CORSIA/CCP not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →