5.2/ 10
Integrity
5.5
Transparency
4.5
Claim Safety
5.0
Documentation
6.0

Audit Analysis

A CDM biomass energy project in India using the AMS-I.C. methodology, with additionality confirmed by Bureau Veritas via a combined test and no unresolved material findings. However, the project-specific baseline, absence of feedstock sustainability data, a fixed 2007 grid emission factor, and a contradictory ERR figure within the same monitoring report limit confidence in the credit quantity. The project is a straightforward fuel-substitution design with reasonable leakage treatment, but several key MRV data points remain unreported.

Red Flags

  • Two different total ERR values (35,236 and 8,874) appear in the same monitoring report dated 2022-11-24, creating ambiguity about the actual credit quantity
  • No feedstock sustainability or carbon content testing data found in any available document for a biomass project
  • Grid emission factor fixed at the 2007 value of 0.81 tCO2/MWh with no evidence of periodic updating
  • Verified ERR figure is not available in the extracted record, preventing independent cross-check of claimed reductions

Credit Vintages

IssuedRetiredAvailable
2012
38,378038,378
Total38,378038,378

Risk Indicators

Additionality

VVB-confirmed combined test

Permanence

No reversal events but no permanence mechanism documented

Leakage

Investigated and confirmed as zero

Baseline

Project-specific, no reassessment documented

Safeguards

Safeguards mentioned, benefit sharing described, but no FPIC

Double-claim

CDM registry; CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-26AMS-I.C. ver. 92

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents