Bundled Solar Project 1 by Aditya Birla Group of Companies

GS-2035 ↗ · current registry ID: GS7547

#478of 1935 in Renewable energy#247of 975 in India#216of 1801 in Gold Standard (GS)#358of 1287 in ACM0002

5.8/ 10
Integrity
6.5
Transparency
5.5
Claim Safety
4.5
Documentation
6.5

Audit Analysis

A Gold Standard solar electricity project in India with a VVB-verified investment additionality test and reasonable safeguards, but significant concerns arise from a large discrepancy between the PDD ex-ante estimate and the monitoring-period claim (the project delivered roughly 407% of the pro-rata expectation), a contradiction in baseline method between documents, and the absence of a verified ERR figure. The project is CORSIA-eligible and uses smart-meter monitoring, which are positive signals, but the over-delivery claim and data inconsistencies warrant caution before crediting.

Red Flags

  • The monitoring report claims 532,065 tCO₂e for a ~2-year period, while the PDD ex-ante estimate is 326,914 tCO₂e for the full 5-year crediting period — the claim is approximately 407% of the pro-rata expectation, indicating a very large over-delivery that requires independent scrutiny.
  • Baseline method is described as 'project-specific' in the verification report but 'jurisdictional' in the monitoring report, creating ambiguity about which baseline was actually applied.
  • No verified ERR figure was found in the extracted record; only the claimed figure is available, limiting independent cross-checking.
  • Reversal events are marked as 'not addressed' in the verification report, though the more recent monitoring report reports none — the verification report's silence is a documentation gap.

Credit Vintages

IssuedRetiredAvailable
2019
5,5955,5950
2020
194,031194,0310
2021
99,24598,913332
Total298,871298,539332

Risk Indicators

Additionality

VVB-verified investment test

Permanence

mixed evidence / unresolved risk

Leakage

0% deduction with quantified justification, reasonable for local-consumption solar

Baseline

Project-specific baseline, method contradicts between documents, no reassessment date stated

Safeguards

FPIC conducted, grievance mechanism present, benefit sharing described

Double-claim

CORSIA-eligible; CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-01ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.