Bundled Wind Energy Project in Maharashtra, India
#1087of 1935 in Renewable energy#565of 975 in India#815of 1459 in CDM (UNFCCC)#353of 806 in AMS-I.D
Audit Analysis
A CDM wind energy project in Maharashtra with a VVB-confirmed investment additionality test and a reasonable 0% leakage deduction for grid-displacement. However, the available record is limited to the 2014 validation phase, with no monitoring reports, no verified ERR figures, and a low extraction confidence rating, leaving significant gaps in post-validation performance data. Three contradictions between the PDD and validation report (ERR magnitude, baseline classification, leakage treatment) introduce data-reliability concerns.
Red Flags
- Total ERR differs by a factor of 10 between the PDD (2,484) and the validation report (24,840) — a material discrepancy that undermines confidence in the claimed credit volume
- No monitoring reports or verified ERR figures were found in the extracted record despite the crediting period (2014–2024) having fully elapsed
- Minimum extraction confidence is rated low, indicating at least one key document was poorly readable or incomplete
- Baseline method is classified as 'project' in the validation report but 'jurisdictional' in the PDD, creating ambiguity about the baseline's robustness
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed investment test
Avoidance project, no reversal risk
0% deduction, reasonable for grid wind
Project-specific per VVB, PDD conflict
Mentioned, benefit sharing described, no FPIC detail
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →