Buyukduz Hydroelectric Power Plant, Turkey
#483of 1935 in Renewable energy#102of 295 in Turkey#249of 1339 in Verra (VCS)#361of 1287 in ACM0002
Audit Analysis
The Büyükdüz hydroelectric project has a solid additionality case (investment test confirmed by the VVB) and a well-documented monitoring protocol using TEIAS meter data, but is undermined by twelve unresolved assessment findings, a project-specific baseline, and a leakage treatment that the most recent verification report describes as 'not addressed.' The project delivered roughly 79% of its pro-rata ex-ante expectation for the elapsed monitoring period, which is conservative but the documentation gaps and contradictions between the 2021 and 2023 verification reports reduce confidence in the overall credit quality.
Red Flags
- Twelve assessment findings raised in the 2023 verification report remain unresolved and must be addressed to Verra's satisfaction before credits can be fully relied upon
- Leakage justification is described as 'not addressed' in the 2023 verification report, contradicting the 2021 report which stated it was 'quantified' — the 0% deduction lacks a clear, current justification
- Baseline method is classified as 'project-specific' in the 2023 verification report, while the 2021 monitoring report described it as 'jurisdictional' — the more recent and authoritative verification document takes precedence, indicating a less robust baseline
- No buffer pool percentage is stated in any available document, leaving no explicit safety margin for potential reversals or over-crediting
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2012 | 34,523 | 34,523 | 0 | |
| 2013 | 70,633 | 22,384 | 48,249 | |
| 2017 | 71,628 | 68,272 | 3,356 | |
| 2018 | 90,144 | 0 | 90,144 | |
| 2019 | 72,669 | 0 | 72,669 | |
| 2020 | 65,970 | 0 | 65,970 | |
| 2021 | 56,318 | 0 | 56,318 | |
| 2022 | 73,500 | 0 | 73,500 | |
| Total | 535,385 | 125,179 | 410,206 |
Risk Indicators
Investment test confirmed by VVB
Hydro avoidance project, low reversal risk
0% deduction, justification not addressed in latest VR
Project-specific baseline, reassessed 2020
FPIC, grievance mechanism, positive EIA
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →