Skip to main content
GSSmall, Low - Impact HydroTurkeyACM0002

Cakirlar Run-off-River Hydro Power Plant

GS-1257 ↗ · current registry ID: GS917

#1353of 1935 in Renewable energy#250of 295 in Turkey#1219of 1801 in Gold Standard (GS)#1046of 1287 in ACM0002

4.6/ 10
Integrity
4.2
Transparency
5.0
Claim Safety
4.8
Documentation
4.5

Audit Analysis

The Çakırlar run-of-river hydro project (17 MW, Turkey) has a VVB-verified additionality assessment and reasonable safeguards, but the verification report explicitly states that VER sales 'significantly improve IRR, making the project bankable,' which directly undermines the additionality claim. Twelve corrective actions were raised during validation, no buffer pool is in place, and the grid emission factor used dates from 2018 while the current monitoring period is 2024, creating a moderate over-crediting risk.

Red Flags

  • The verification report states that VER sales 'significantly improve IRR, making the project bankable,' which is a direct admission that the project would not be financially viable without carbon credits, undermining the additionality claim.
  • Twelve corrective actions (CARs) and nine clarifications (CLs) were raised during validation, indicating significant documentation and methodological gaps at the outset.
  • The grid emission factor of 0.4607 tCO2/MWh is from 2018, yet the current monitoring period is 2024; if Turkey's grid has decarbonised over six years, the baseline may overstate emission reductions.
  • No buffer pool percentage is stated in any available document, and the verification report does not explicitly address reversal risk, leaving permanence protection undefined.

Credit Vintages Exhausted

IssuedRetiredAvailable
2013
27,05027,0500
2014
28,11128,1110
2015
26,42626,4260
2016
14,07714,0770
Total95,66495,6640

Risk Indicators

Additionality

VVB-verified but carbon-revenue dependent

Permanence

reversal not explicitly addressed in verification

Leakage

0% deduction, reasonable for run-of-river hydro

Baseline

Project-specific baseline; grid EF from 2018

Safeguards

FPIC, grievance mechanism, benefit sharing documented

Double-claim

CORSIA and CCP status not stated in available documents

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-01ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents