Cepco Wind Power Project in Gujarat

CDM-6031 ↗

#67of 1935 in Renewable energy#40of 975 in India#41of 1459 in CDM (UNFCCC)#23of 806 in AMS-I.D

6.8/ 10
Integrity
7.0
Transparency
6.0
Claim Safety
7.0
Documentation
7.0

Audit Analysis

The Cepco Wind Power Project is a standard CDM wind displacement project (AMS I.D) with VVB-confirmed additionality via an investment test and a grid-emission-factor baseline appropriate for the methodology. Delivery was conservative at roughly 77% of the pro-rata ex-ante expectation for the monitored period, and no reversal or leakage risks are material for a wind project. Main concerns are transparency gaps in the original PDD (nine corrective actions at validation) and a contradiction between documents on whether the baseline is project-specific or jurisdictional.

Red Flags

  • Nine corrective actions were raised at validation, including missing DNA approval letter, opaque applicability criteria, unclear project boundary and metering points, and an unrealistic crediting-period start date — all subsequently addressed but indicating a weak initial PDD.
  • The monitoring report characterises the baseline as 'project' while the validation report (2012) describes it as 'jurisdictional'; for AMS I.D the grid-emission-factor approach is jurisdictional, so the monitoring report's label is inconsistent with the methodology.
  • Leakage justification is contradictory: the 2012 validation report states leakage was 'deemed negligible' while the 2023 monitoring report says it was 'quantified'; the 0% deduction is appropriate for wind but the inconsistent framing weakens the audit trail.

Credit Vintages

IssuedRetiredAvailable
2023
44,787044,787
Total44,787044,787

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Wind displacement – no reversal risk

Leakage

0% deduction, appropriate for grid-connected wind

Baseline

Grid-EF baseline but method label contradicts across documen

Safeguards

Safeguards and benefit-sharing mentioned; FPIC and grievance

Double-claim

CORSIA and CCP status not stated in available documents

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-27AMS I.D

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents