Skip to main content
CDMHydroThailandAMS-I.D

Chao Phraya Hydropower Project

CDM-8853 ↗

#485of 1935 in Renewable energy#11of 48 in Thailand#315of 1459 in CDM (UNFCCC)#171of 806 in AMS-I.D

5.8/ 10
Integrity
6.5
Transparency
5.5
Claim Safety
6.0
Documentation
4.5

Audit Analysis

The Chao Phraya Hydropower Project is a small-scale CDM hydro project with a standard jurisdictional baseline and VVB-confirmed investment additionality, but it carries a heavy burden of 22 material findings (mostly documentation) and a notable pro-rata under-delivery of roughly half the expected emission reductions for the monitored period. The project is methodologically sound in its core design but suffers from weak documentation quality and limited monitoring coverage.

Red Flags

  • 22 material findings reported in the verification report, including a generator capacity discrepancy (7,294 kVA nameplate vs. 6.2 MW in the PDD) and insufficient financial analysis substantiation
  • Pro-rata under-delivery: the monitoring report (2013–2014) records 34,182 tCO₂e against a pro-rata expectation of ~69,934 tCO₂e (244,769 × 2/7), representing only ~49% of expected reductions
  • Verified ERR figure for the monitoring period was not extracted from the monitoring report, leaving a gap in the audit trail
  • Monitoring covers only 2 of the 7 crediting years (2013–2014 of 2013–2019), limiting confidence in lifetime delivery

Credit Vintages

IssuedRetiredAvailable
2016
34,163034,163
Total34,163034,163

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Avoidance project, no inherent reversal risk

Leakage

0% deemed negligible, appropriate for hydro

Baseline

Jurisdictional grid EF, standard for hydro

Safeguards

Safeguards and benefit sharing mentioned; FPIC and grievance

Double-claim

CORSIA and CCP status not stated in available documents

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-27AMS-I.D

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents