Chieng Cong Hydropower Project
#208of 1935 in Renewable energy#14of 80 in Vietnam#124of 1459 in CDM (UNFCCC)#76of 806 in AMS-I.D
Audit Analysis
The Chieng Cong Hydropower Project is a small-scale CDM hydro project in Vietnam with a VVB-confirmed investment additionality test and a reasonable 0% leakage deduction. However, the verification process surfaced 26 corrective action requests, equipment specifications that deviated from the PDD, and a contradiction in baseline methodology between the PDD and monitoring report. Several key verification parameters (FNRB, usage rate, CORSIA/CCP status) are absent from the extracted record, limiting full confidence in the credit's robustness.
Red Flags
- 26 Corrective Action Requests raised and closed during verification, indicating significant discrepancies between the PDD and actual project implementation
- Baseline methodology contradicts between the PDD (project-specific) and the monitoring report (jurisdictional), creating ambiguity about the baseline basis
- Generator capacity increased from 1,000 kW to 1,250 kW without apparent PDD amendment, and electricity meters were reduced from six to two by EVN decision
- FNRB value, usage rate, CORSIA eligibility, and CCP status are all absent from the extracted record, leaving key claim-safety parameters unverifiable
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2012 | 23,425 | 0 | 23,425 | |
| 2013 | 13,935 | 0 | 13,935 | |
| Total | 37,360 | 0 | 37,360 |
Risk Indicators
VVB-confirmed investment test
hydro asset low-risk but unaddressed
0% deduction, justified as negligible for grid-connected hyd
Method contradictory across documents; grid EF from 2007
Mentioned with benefit sharing; FPIC and grievance mechanism
CORSIA and CCP status not stated in available records
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →