China Qinghai 42MW Jiangyuan hydropower project
#756of 1935 in Renewable energy#371of 1084 in China#527of 1459 in CDM (UNFCCC)#586of 1287 in ACM0002
Audit Analysis
A 42 MW run-of-river hydropower project in Qinghai, China, registered under CDM with a combined additionality test confirmed by the VVB. The project carries significant documentation concerns (12 material findings, 4 corrective actions) and a baseline-method contradiction between the validation report and the 2012 monitoring report, but as an avoidance-type hydro project it faces lower permanence risk. Overall a mid-range project with moderate data gaps and unresolved baseline questions.
Red Flags
- Twelve material findings in the validation report, including concerns that the project IRR and equity IRR are poor and that development would be at significant risk without CER revenue, undermining the robustness of the additionality case
- Baseline method is described as 'project-specific' in the validation report (2010) but 'jurisdictional' in the 2012 monitoring report — an unresolved contradiction that affects the credibility of the baseline
- No buffer pool is applied and no baseline reassessment date is recorded in the available documents
- Total verified ERR is not stated in the extracted record, preventing an independent cross-check of claimed versus verified credits
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2012 | 218,388 | 0 | 218,388 | |
| 2013 | 140,907 | 0 | 140,907 | |
| Total | 359,295 | 0 | 359,295 |
Risk Indicators
VVB-confirmed combined test, but financial-viability finding
Avoidance-type hydro; no reversal events
0% deduction with 'deemed negligible' justification; consist
Method contradicts between validation (project) and monitori
Safeguards mentioned and benefit sharing described, but FPIC
CORSIA and CCP statuses not stated in available documents; d
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →