China Resources New Energy Lufeng Chengmei Wind Farm Project
#834of 1935 in Renewable energy#424of 1084 in China#584of 1459 in CDM (UNFCCC)#647of 1287 in ACM0002
Audit Analysis
A CDM wind project with a solid investment-test additionality assessment confirmed by ERM and a jurisdictional baseline, but the available record is limited to validation-stage documents from 2012 with no monitoring or verification reports. A seven-fold discrepancy between the PDD and validation report on total emissions reductions (588,553 vs 84,079 tCO₂e) is a material concern, and the low extraction confidence further limits confidence in the data.
Red Flags
- Seven-fold discrepancy in total ERR between the PDD (588,553 tCO₂e) and the validation report (84,079 tCO₂e); the validation report figure was privileged as the VVB's authoritative assessment, but the unexplained gap raises over-crediting risk if the PDD figure was used in any issuance
- No monitoring reports or verification reports are present in the extracted record; actual performance against the claimed 84,079 tCO₂e over the 2012–2019 crediting period cannot be confirmed
- Minimum extraction confidence is rated low, indicating at least one key document was poorly readable, reducing reliability of all extracted figures
- Leakage justification is inconsistent across documents: the validation report states 'deemed negligible' while an appendix (earlier, 2012-02-08) references a 'quantified' approach
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed investment test
Avoidance project, no reversal risk
Negligible, justified for grid-displacement
Jurisdictional, no reassessment data
Mentioned, benefit sharing described, no FPIC/grievance
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →