China Resources Weichang Yudaokou Yangbaishun 49.5 MW Wind Power Project

CDM-5836 ↗

#1095of 1935 in Renewable energy#610of 1084 in China#826of 1459 in CDM (UNFCCC)#854of 1287 in ACM0002

5.0/ 10
Integrity
6.5
Transparency
3.5
Claim Safety
5.5
Documentation
3.0

Audit Analysis

A 49.5 MW onshore wind project in China validated under CDM with a jurisdictional grid baseline and VVB-confirmed additionality, but the available record is limited to the validation stage with no monitoring data, seven material findings in the PDD, and low extraction confidence. The ERR figures in the PDD and validation report are internally consistent (annual × 7-year total), but the absence of verified delivery data and safeguards documentation limits confidence in the project's ongoing performance.

Red Flags

  • Seven material findings (CAR-1 through CAR-6, CL-8) in the validation report, including missing DNA approval letter, outdated additionality and grid-EF tools, and mismatched financial parameters in the PDD
  • No monitoring reports or verified ERR figures found in the extracted record — delivery performance cannot be assessed
  • Low extraction confidence across the document set, indicating at least one key document was poorly readable
  • FPIC and grievance mechanism not documented in the available record despite safeguards being mentioned

Credit Vintages

No issuances recorded on the registry.

Risk Indicators

Additionality

VVB-confirmed combined test

Permanence

Avoidance project, no reversal risk

Leakage

0% deemed negligible, appropriate for wind-to-grid

Baseline

Jurisdictional grid EF, standard for CDM wind

Safeguards

Mentioned and benefit sharing described, but FPIC and grieva

Double-claim

CORSIA and CCP status not stated in available documents

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-27ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents