China Resources Weichang Yudaokou Yangbaishun 49.5 MW Wind Power Project
#1095of 1935 in Renewable energy#610of 1084 in China#826of 1459 in CDM (UNFCCC)#854of 1287 in ACM0002
Audit Analysis
A 49.5 MW onshore wind project in China validated under CDM with a jurisdictional grid baseline and VVB-confirmed additionality, but the available record is limited to the validation stage with no monitoring data, seven material findings in the PDD, and low extraction confidence. The ERR figures in the PDD and validation report are internally consistent (annual × 7-year total), but the absence of verified delivery data and safeguards documentation limits confidence in the project's ongoing performance.
Red Flags
- Seven material findings (CAR-1 through CAR-6, CL-8) in the validation report, including missing DNA approval letter, outdated additionality and grid-EF tools, and mismatched financial parameters in the PDD
- No monitoring reports or verified ERR figures found in the extracted record — delivery performance cannot be assessed
- Low extraction confidence across the document set, indicating at least one key document was poorly readable
- FPIC and grievance mechanism not documented in the available record despite safeguards being mentioned
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed combined test
Avoidance project, no reversal risk
0% deemed negligible, appropriate for wind-to-grid
Jurisdictional grid EF, standard for CDM wind
Mentioned and benefit sharing described, but FPIC and grieva
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →