Chongqing Siyanping 49.3MW Wind Power Project
#1010of 1935 in Renewable energy#553of 1084 in China#743of 1459 in CDM (UNFCCC)#794of 1287 in ACM0002
Audit Analysis
A 49.3 MW onshore wind project in Chongqing, China, validated under CDM methodology ACM0002 v19.0 with a jurisdictional grid-emission-factor baseline. The project is low-risk in design (wind displacing grid electricity, negligible leakage, no reversal risk), but the extracted record lacks explicit confirmation of the additionality test, a monitoring report, and several MRV parameters, limiting confidence in the full verification chain.
Red Flags
- Additionality test type and VVB confirmation are not stated in the extracted record, leaving the additionality assessment unverified from available documents
- No monitoring report is present in the evidence set; the only verification document is the 2019 validation report, so post-validation performance is unconfirmed
- The PDD (486,710 tCO₂e) and validation report (69,530 tCO₂e) report different ERR figures; although the ratio (~7×) is consistent with a 7-year crediting period, the discrepancy was not explicitly reconciled in the documents
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2012 | 92,383 | 0 | 92,383 | |
| 2013 | 109,347 | 0 | 109,347 | |
| Total | 201,730 | 0 | 201,730 |
Risk Indicators
Test type not stated in extracted record
Avoidance project, no reversal risk
0% deemed negligible, appropriate for wind
Jurisdictional grid EF, reassessed 2019
Safeguards and benefit sharing mentioned; FPIC and grievance
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →