The Chorokhi Hydro Power Plant is a VCS-registered small-scale hydro project in Georgia with a VVB-confirmed investment additionality test, no reversal events, and a quantified zero-leakage justification. However, a contradiction between the verification report (project-specific baseline) and the monitoring report (jurisdictional baseline), combined with a low extraction confidence across the document set and several unstated fields (buffer pool, CORSIA, CCP), limits confidence in the overall data quality.
Red Flags
- Baseline method is stated as 'project' in the 2024 verification report but 'jurisdictional' in the 2024 monitoring report — an unresolved contradiction that affects the robustness of the credit calculation
- CORSIA eligibility and CCP status are both unstated, creating uncertainty about dual-channel or double-claiming risk
- Minimum extraction confidence is rated low, indicating at least one key document was poorly readable and the extracted facts may be incomplete
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2017 | 128,552 | 128,552 | 0 | |
| 2019 | 181,382 | 166,582 | 14,800 | |
| 2020 | 53,936 | 12,586 | 41,350 | |
| 2021 | 8,974 | 5,951 | 3,023 | |
| Total | 372,844 | 313,671 | 59,173 |
Risk Indicators
VVB-confirmed investment test
No reversals
0% quantified, reasonable for hydro
Project-specific; VR/MR contradiction
FPIC, grievance mechanism, safeguards documented
CORSIA and CCP status unstated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →