Daode 49.5MW Wind Power Project

CDM-3903 ↗

#210of 1935 in Renewable energy#70of 1084 in China#126of 1459 in CDM (UNFCCC)#149of 1287 in ACM0002

6.3/ 10
Integrity
6.0
Transparency
6.5
Claim Safety
7.0
Documentation
5.5

Audit Analysis

The Daode 49.5 MW wind project is a straightforward CDM renewable-energy credit with a jurisdictional grid-emission-factor baseline and VVB-confirmed additionality. No material findings or corrective actions were reported, and the 0% leakage deduction is appropriate for a wind project. The principal concern is that the verified emissions reduction (99,524 tCO₂e) covers only the first ~1.8 years of a 7-year crediting period and represents roughly 55% of the pro-rata PDD expectation, suggesting the ex-ante assumptions were optimistic.

Red Flags

  • Verified ERR of 99,524 tCO₂e for ~1.8 years of operation is only ~55% of the pro-rata PDD expectation (~179,200 tCO₂e), indicating the PDD overestimated output or capacity factor
  • Monitoring data available only through September 2019; no subsequent monitoring reports found for the remaining ~5 years of the crediting period (through December 2024)
  • Additionality test type (investment, barrier, or regulatory) is not specified in the extracted record, limiting assessment of robustness

Credit Vintages

IssuedRetiredAvailable
2012
96,029096,029
2014
158,2360158,236
Total254,2650254,265

Risk Indicators

Additionality

VVB-confirmed (CTC)

Permanence

Avoidance project, no reversal risk

Leakage

Negligible, appropriate for wind

Baseline

Jurisdictional grid EF (2017)

Safeguards

Mentioned but not detailed

Double-claim

CDM; CORSIA/CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-27ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents