Datang Ningxia Taiyangshan Phase II Wind Farm Project
#1520of 1935 in Renewable energy#959of 1084 in China#1292of 1459 in CDM (UNFCCC)#1159of 1287 in ACM0002
Audit Analysis
A CDM wind farm project in China with a jurisdictional baseline and appropriate leakage treatment, but significant data gaps in additionality documentation, no monitoring reports available, and a seven-fold discrepancy between the PDD and validation report on total emissions reductions. Three material findings requiring corrective action, including incorrect baseline calculations, further erode confidence in the project's data integrity.
Red Flags
- Seven-fold discrepancy in total ERR: PDD (July 2019) states 524,097 tCO2e while the validation report (September 2019) states 74,871 tCO2e — a factor of ~7 difference that undermines data reliability
- Material finding CAR-1 identifies incorrect baseline emissions and emission reduction calculations for partial years 2019 and 2026, requiring corrective action
- No monitoring reports or verification reports found in the extracted record — actual credit delivery cannot be independently confirmed
- Additionality test type and VVB confirmation are not stated in the available documents, leaving a critical gap in the additionality evidence chain
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
Test type not stated in extracted record
Avoidance project, no reversal risk
0% deemed negligible, appropriate for wind
Jurisdictional, 2019 grid EF
Mentioned but FPIC and grievance not documented
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →