Dayan River Stage I and Dayan River Stage II 17.6MW Bundled Hydropower Project

CDM-3866 ↗

#45of 1935 in Renewable energy#8of 1084 in China#31of 1459 in CDM (UNFCCC)#29of 1287 in ACM0002

6.9/ 10
Integrity
7.0
Transparency
6.5
Claim Safety
7.0
Documentation
7.0

Audit Analysis

A standard CDM hydropower project (ACM0002 v11) with a VVB-confirmed combined additionality test and a jurisdictional grid-emission-factor baseline. The project delivered roughly 36% of its pro-rata ex-ante expectation in the first monitoring period, indicating the lifetime estimate was optimistic but eliminating over-crediting risk. Seven corrective actions were raised at validation (documentation and data-source issues) but none persisted into monitoring.

Red Flags

  • The first monitoring period (Feb–Oct 2011) yielded only ~36% of the pro-rata ex-ante expectation (15,829 vs ~43,500 tCO2e), suggesting the lifetime estimate of 457,646 tCO2e may have been optimistic or that 2011 flows were atypically low.
  • The grid emission factor of 0.78795 tCO2/MWh is from 2009; China's grid has become cleaner since, meaning the actual per-MWh avoidance is lower than the credit value implies.
  • CORSIA eligibility and CCP status are not stated in any available document, leaving dual-channel risk unassessed.

Credit Vintages

No issuances recorded on the registry.

Risk Indicators

Additionality

VVB-confirmed combined test

Permanence

Avoidance project, no reversal risk

Leakage

0% deemed negligible, reasonable for grid-displacement hydro

Baseline

Jurisdictional grid EF (ACM0002 standard)

Safeguards

Mentioned but FPIC and grievance mechanism not detailed

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-28ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents