Expansion Project of Huadian Inner Mongolia Huitengxile Wind Farm
#214of 1935 in Renewable energy#71of 1084 in China#129of 1459 in CDM (UNFCCC)#153of 1287 in ACM0002
Audit Analysis
A CDM wind expansion project in Inner Mongolia with a solid combined additionality test verified by TÜV SÜD and a jurisdictional grid baseline. The project is inherently low-risk on permanence (no biogenic storage), but transparency is weakened by a missing verified ERR figure, several unreported monitoring parameters, and a notable discrepancy between two monitoring reports' claimed emission reductions. All material findings from validation were resolved, and no corrective actions remain outstanding.
Red Flags
- Two monitoring reports (March 2012 and September 2012) report materially different claimed emission reductions (44,316 vs 24,204 tCO₂e), raising a data-consistency concern even if they cover different reporting periods
- Total verified ERR figure is absent from the extracted record, preventing independent cross-check of the claimed 24,204 tCO₂e
- No grievance mechanism or FPIC documentation found in the available records, despite safeguards being mentioned in general terms
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2010 | 72,605 | 0 | 72,605 | |
| 2011 | 48,874 | 0 | 48,874 | |
| 2012 | 44,316 | 0 | 44,316 | |
| 2013 | 24,204 | 0 | 24,204 | |
| Total | 189,999 | 0 | 189,999 |
Risk Indicators
Combined test, VVB-verified
Wind – no reversal risk
0% – negligible, grid-fed
Jurisdictional grid EF (2007)
Mentioned; FPIC & grievance not documented
CORSIA/CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →