Fener Wind Power Project

ICR-423 ↗

#674of 1935 in Renewable energy#8of 75 in TR#13of 154 in Intl. Carbon Registry (ICR)#520of 1287 in ACM0002

5.5/ 10
Integrity
6.5
Transparency
4.5
Claim Safety
6.5
Documentation
3.5

Audit Analysis

The Fener Wind Power Project is a grid-connected wind avoidance project in Turkey using a jurisdictional baseline and a combined additionality test, with no reversal events and a reasonable 0% leakage deduction. However, the documentation record is thin—only a PDD is available, no verification or monitoring report is present, and the VVB identity is not stated. The claimed ERR of 49,291 tCO₂e for the 2021–2025 monitoring window appears well below the pro-rata expectation of roughly 154,500 tCO₂e derived from the 386,379 tCO₂e lifetime ex-ante estimate, though the absence of a verified figure prevents definitive assessment.

Red Flags

  • No verification report or monitoring report is present in the evidence record; the VVB name is not stated, making independent verification of the additionality test and ERR figures impossible to confirm.
  • The claimed ERR of 49,291 tCO₂e for the four-year monitoring period (2021–2025) is only about 32% of the pro-rata expectation (~154,500 tCO₂e) derived from the 386,379 tCO₂e lifetime ex-ante estimate, raising questions about the robustness of the ex-ante capacity-factor assumptions.
  • A contradiction exists between two PDD versions (November vs December 2025) on whether benefit-sharing is described, indicating internal inconsistency in project documentation.

Credit Vintages

IssuedRetiredAvailable
2021
6,29606,296
2022
12,289012,289
2023
12,289012,289
2024
12,289012,289
2025
12,289012,289
2026
28,535028,535
2027
67,301067,301
2028
67,301067,301
2029
67,301067,301
2030
67,301067,301
2031
33,189033,189
Total386,3800386,380

Risk Indicators

Additionality

Combined test present but VVB verification not stated

Permanence

Avoidance project, no reversal events, low inherent risk

Leakage

0% deduction, deemed negligible, appropriate for grid wind

Baseline

Jurisdictional method, but last reassessment date not stated

Safeguards

FPIC, grievance mechanism, and safeguards all confirmed

Double-claim

CORSIA and CCP status both not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-02ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents