Fengguang 24.9MW Hydropower Project in Guangdong Province, China
#938of 1935 in Renewable energy#494of 1084 in China#678of 1459 in CDM (UNFCCC)#735of 1287 in ACM0002
Audit Analysis
The Fengguang 24.9 MW hydropower project is a standard CDM small-scale hydro installation under ACM0002 with a 7-year crediting period. ERR claimed and verified figures match exactly at 454,251 tCO₂e, and no reversal events were reported. However, the additionality test type is not explicitly stated in the extracted record, four administrative material findings (versioning mismatches) were flagged with corrective actions required, and two contradictions between the validation and monitoring reports (leakage justification and baseline method) reduce confidence in data consistency.
Red Flags
- Additionality test type and VVB confirmation are not stated in any extracted document, leaving a critical CDM requirement unverified in the available record
- Four material findings in the monitoring report flag versioning mismatches (PDD form, methodology, emission-factor tool, grid EF year) requiring corrective actions
- Contradiction between validation report (leakage 'deemed negligible') and monitoring report (leakage 'quantified') creates ambiguity in the leakage treatment
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2010 | 9,101 | 0 | 9,101 | |
| 2011 | 60,203 | 0 | 60,203 | |
| 2012 | 152,076 | 0 | 152,076 | |
| 2013 | 17,374 | 0 | 17,374 | |
| Total | 238,754 | 0 | 238,754 |
Risk Indicators
Test type not stated in extracted record; CDM validation imp
no reversal events, but permanence me
0% deduction with quantified justification per monitoring re
Project-specific baseline with 2015 grid EF; standard for AC
Safeguards and benefit-sharing mentioned; FPIC and grievance
CORSIA and CCP eligibility not stated in extracted record
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →