Ganhekou V 201MW Wind Farm Project
#1238of 1935 in Renewable energy#723of 1084 in China#965of 1459 in CDM (UNFCCC)#961of 1287 in ACM0002
Audit Analysis
The Ganhekou V 201MW Wind Farm is a CDM-registered wind project with a jurisdictional baseline and VVB-confirmed additionality, but the available record is limited to validation-stage documents with no monitoring data. Nine material findings and eight corrective actions in the validation report reveal significant PDD drafting errors, and the absence of any verified emission reduction figures prevents independent validation of the 341,946 tCO2e lifetime claim.
Red Flags
- Nine material findings and eight corrective actions in the validation report indicate substantial PDD drafting errors, including incorrect OM/BM weight values, missing ex-ante parameters, and two monitored parameters (EGExport, EGImport) omitted from the PDD
- No monitoring report or verified emission reduction figure is available in the extracted record, making it impossible to confirm whether the 341,946 tCO2e lifetime claim was actually delivered
- The validation report notes a 62-day delay in the notification of intention to renew the crediting period, suggesting administrative compliance gaps
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2011 | 175,730 | 0 | 175,730 | |
| 2013 | 444,025 | 0 | 444,025 | |
| Total | 619,755 | 0 | 619,755 |
Risk Indicators
VVB-confirmed
Avoidance project, no reversals
0% justified for grid-connected wind
Jurisdictional, reassessed 2018
Mentioned but FPIC and grievance not documented
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →