4.6/ 10
Integrity
4.5
Transparency
4.5
Claim Safety
4.5
Documentation
5.0

Audit Analysis

A small Chinese hydropower project under CDM with a jurisdictional grid baseline and reasonable leakage treatment, but significant data gaps around additionality verification, monitoring, and a major 7× discrepancy between the PDD and validation report on total emissions reductions. The project's avoidance-based design (displacing grid electricity) limits permanence risk, but the absence of monitoring data and safeguards documentation weakens overall confidence.

Red Flags

  • The PDD (2019-05-20) states a total ERR of 3,041,626 tCO₂e while the validation report (2019-05-21) records only 434,518 tCO₂e — a roughly 7× discrepancy that raises serious questions about the reliability of the project's emissions accounting.
  • Additionality test type and VVB confirmation are not stated in any available document, leaving a core CDM requirement unverified in the extracted record.
  • No monitoring period, monitoring data, or usage tracking information is present, making it impossible to assess whether the project is actually delivering its claimed reductions.

Credit Vintages

No issuances recorded on the registry.

Risk Indicators

Additionality

Test type and VVB confirmation not stated in available docum

Permanence

Avoidance project (grid displacement); no reversal risk iden

Leakage

0% deduction, deemed negligible — appropriate for grid-displ

Baseline

Jurisdictional grid baseline, EF 0.4712 (2017), reassessed 2

Safeguards

Safeguards mentioned and benefit sharing described, but FPIC

Double-claim

CORSIA and CCP status not stated in available documents

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-29ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents