Gansu Qilinsi 111MW Hydropower Project
#1544of 1935 in Renewable energy#991of 1084 in China#1334of 1459 in CDM (UNFCCC)#1177of 1287 in ACM0002
Audit Analysis
A 111 MW CDM hydropower project in China with a jurisdictional grid baseline and appropriate leakage treatment, but the extracted record contains only validation-stage documents with no monitoring data, an unconfirmed additionality assessment, and a significant seven-fold discrepancy between the PDD and validation report on lifetime emissions reductions. The project's fundamental design is sound for a hydro avoidance project, but the absence of verified performance data and the ERR contradiction limit confidence in the claims.
Red Flags
- Seven-fold discrepancy in lifetime ERR: the PDD (2019-05-20) states 1,473,724 tCO2e while the validation report (2019-05-21) states 210,532 tCO2e — a factor of ~7 difference that is unexplained in the available documents
- No monitoring reports or verified ERR figures found in the extracted record; the crediting period ended 2023-12-05 but no performance data is available
- Additionality test type and VVB confirmation are not stated in the extracted record, leaving the additionality assessment unverified
- Three material findings in the PDD (missing load factor, project boundary, and post-registration change summary) were noted by the VVB
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2011 | 287,216 | 0 | 287,216 | |
| 2012 | 314,335 | 0 | 314,335 | |
| 2013 | 307,723 | 0 | 307,723 | |
| Total | 909,274 | 0 | 909,274 |
Risk Indicators
Test type and VVB confirmation not found in record
Hydro avoidance project, no reversal risk
0% deemed negligible, appropriate for grid-connected hydro
Jurisdictional grid EF, reassessed 2019
Mentioned and benefit sharing described, but FPIC and grieva
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →