Ganxipo Hydroelectric Project
#1309of 1935 in Renewable energy#790of 1084 in China#1035of 1459 in CDM (UNFCCC)#1017of 1287 in ACM0002
Audit Analysis
The Ganxipo Hydroelectric Project is a small CDM-registered hydro scheme in China using a jurisdictional grid baseline. While the project type (avoidance of grid electricity) carries low permanence risk and the 0% leakage deduction is reasonable, the extracted record contains a critical gap on additionality and a seven-fold discrepancy between the PDD's ex-ante estimate (1,011,976 tCO₂e) and the verified figure (144,568 tCO₂e), raising material over-crediting concerns. A grid emission factor contradiction between the validation and monitoring reports further undermines confidence in the baseline.
Red Flags
- PDD ex-ante estimate of 1,011,976 tCO₂e is roughly 7× the verified 144,568 tCO₂e for the same crediting period (2014–2021), indicating the original claim was substantially overstated relative to actual generation
- Grid emission factor differs between the validation report (0.4587 tCO₂/kWh, 2017) and the monitoring report (0.3112 tCO₂/kWh), creating uncertainty about which baseline parameter was actually applied to credit calculations
- Additionality test type and VVB confirmation are not stated in any extracted document, leaving a core CDM requirement unverified in the available record
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
Not stated in extracted record
Avoidance project, no reversal risk
0% deemed negligible, consistent with hydro
Jurisdictional but grid EF contradicts
Mentioned, benefit sharing described, FPIC/grievance not sta
CCP and CORSIA status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →