Generation of electricity from 9.6 MW capacity wind mills by Sun-n-Sand Hotels Pvt. Ltd. at Bhambarwadi, Maharashtra

CDM-1542 ↗

#160of 975 in India#195of 1459 in CDM (UNFCCC)#116of 806 in AMS-I.D

6.1/ 10
Integrity
6.5
Transparency
5.5
Claim Safety
6.0
Documentation
6.5

Audit Analysis

A 9.6 MW CDM wind project in Maharashtra with a VVB-confirmed investment additionality test and a jurisdictional grid baseline. The project is technically straightforward, but a high number of corrective action requests during verification, a dated 2007 grid emission factor, and an internal contradiction in claimed emission reduction figures temper confidence in the credit volume.

Red Flags

  • 13 Corrective Action Requests and 8 Clarification Requests were raised during verification, indicating a non-trivial number of issues that had to be resolved before credit issuance.
  • The monitoring report contains an internal contradiction on total claimed emissions reductions (43,335 vs 31,652 tCO2e), undermining confidence in the reported credit volume.
  • The grid emission factor of 0.9064 tCO2/MWh is drawn from 2007 data; India's grid mix has shifted since then, so the baseline may overstate the displacement benefit.
  • The monitoring report is dated September 2022 but covers a monitoring period ending December 2015, a gap of nearly seven years that raises questions about timeliness of MRV reporting.

Credit Vintages

IssuedRetiredAvailable
2009
8,94008,940
2010
14,433014,433
2011
12,945012,945
2012
14,208014,208
2013
12,216012,216
2023
74,972074,972
Total137,7140137,714

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

mixed evidence / unresolved risk

Leakage

Quantified, deemed negligible (0%)

Baseline

Jurisdictional but 2007 grid EF, no reassessment stated

Safeguards

Mentioned; FPIC and grievance details not found

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-29AMS I.D: “Grid connected renewable electricity generation”

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents