Audit Analysis
A CDM biomass energy project (bagasse power at a sugar mill) with VVB-confirmed additionality and a reasonable 81% verified-to-claimed delivery ratio, but undermined by a project-specific baseline, 23 corrective actions flagged in the PDD, and several key MRV parameters (FNRB, usage monitoring, buffer pool) left unstated in the available record.
Red Flags
- 23 corrective actions were required on the PDD, spanning additionality documentation, baseline scenario corrections, monitoring plan gaps, and data-source issues — indicating the original submission had substantial methodological weaknesses
- FNRB value, usage monitoring method, and buffer pool percentage are all absent from the extracted record, leaving key MRV and permanence parameters unverifiable
- Crediting period dates differ between the PDD (2007-11-09 to 2017-11-09) and the 2012 monitoring report (2008-02-01 to 2018-01-31), creating ambiguity about the actual registration window
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2009 | 6,947 | 0 | 6,947 | |
| 2010 | 8,935 | 0 | 8,935 | |
| 2011 | 50,913 | 0 | 50,913 | |
| 2013 | 30,414 | 0 | 30,414 | |
| Total | 97,209 | 0 | 97,209 |
Risk Indicators
VVB-confirmed combined test
low inherent risk for energy project
0% deemed negligible; thin justification
Project-specific; 2006 grid EF
Safeguards and benefit sharing mentioned; FPIC and grievance
CORSIA and CCP status both not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →