Skip to main content
VCSEnergy industries (renewable/non-renewable sources)India Registry: RegisteredACM0002

Grid connected bundled wind power project in Gujarat managed by Enercon (India) Limited

VCS-370 ↗

#729of 1935 in Renewable energy#355of 975 in India#437of 1339 in Verra (VCS)#570of 1287 in ACM0002

5.4/ 10
Integrity
5.5
Transparency
5.5
Claim Safety
5.5
Documentation
5.0

Audit Analysis

A long-running grid-connected wind project in Gujarat with a sound jurisdictional baseline and VVB-verified investment additionality, but burdened by an extensive list of material findings (calibration delays, missing data, an unaddressed Great Indian Bustard threat) that were closed out. The project delivered roughly 66% of its pro-rata ex-ante expectation for the elapsed monitoring period, indicating conservative crediting. Low extraction confidence and several null fields (CORSIA, CCP, FNRB) limit the depth of assurance.

Red Flags

  • Threat to the Great Indian Bustard (a critically endangered species) was not addressed in the monitoring report (CL#08), raising a significant biodiversity concern for a Gujarat wind project.
  • Meter calibration at the Bhogat substation was delayed beyond the registered frequency (last calibrated 2013/2016, next due 2021), requiring a 0.2% correction factor and casting doubt on the precision of generation data.
  • 30+ material findings, 8 CARs, 9 CRs, and 1 FAR were raised across verification cycles, indicating persistent monitoring and documentation quality issues despite all being closed.
  • CORSIA eligibility and CCP status are not stated in any available document, leaving the double-claiming risk unassessed.

Credit Vintages

IssuedRetiredAvailable
2008
24,19424,094100
2009
26,00326,0030
2010
24,10924,1090
2011
23,94023,9400
2012
24,97824,9780
2013
5,5795,5790
2017
21,08521,0850
2018
23,27023,2700
2019
23,97323,9730
2020
19,65419,183471
2021
23,79922,3271,472
Total240,584238,5412,043

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Wind power – no reversal risk

Leakage

0% – negligible for grid feed-in

Baseline

Jurisdictional, reassessed 2018

Safeguards

FPIC & grievance present; Bustard threat unaddressed

Double-claim

CORSIA & CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-09ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents