Grid connected natural gas based electricity generation power plant at Vemagiri, Andhra Pradesh, India
#319of 1329 in Industrial#430of 975 in India#595of 1459 in CDM (UNFCCC)#7of 19 in AM0029
Audit Analysis
A CDM coal-to-natural-gas fuel-switch project validated by Bureau Veritas with confirmed additionality, but the PDD required 13+ corrective actions at validation, indicating substantial initial design deficiencies. The first monitoring period delivered only ~13% of the pro-rata PDD expectation, which is protective against over-crediting but raises questions about the original ex-ante estimate. Multiple contradictions between the PDD, validation report, and monitoring report reduce confidence in the project's data consistency.
Red Flags
- 13+ corrective actions required at validation, including incorrect benchmark investment analysis, incomplete common practice analysis, and insufficient natural gas availability demonstration — indicating a substantially deficient PDD
- First monitoring period (2 years) claimed only 584,460 tCO2e versus a pro-rata PDD expectation of ~4.6 million tCO2e, a ~13% delivery ratio that suggests the original ex-ante estimate was wildly over-optimistic
- Baseline method is contradictory: the validation report (Oct 2012) describes a project-specific baseline while the monitoring report (Nov 2016) labels it jurisdictional — a fundamental characterization discrepancy for a fuel-switch project
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2017 | 623,283 | 0 | 623,283 | |
| Total | 623,283 | 0 | 623,283 |
Risk Indicators
VVB-confirmed combined test
no reversals reported
Quantified per monitoring report but no specific value
Project-specific per validation; contradicted by monitoring
Safeguards mentioned; FPIC and grievance mechanism not state
CORSIA and CCP status not stated in extracted record
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →