Grid Connected Solar PV Plant in Rajasthan
#1423of 1935 in Renewable energy#777of 975 in India#1162of 1459 in CDM (UNFCCC)#467of 806 in AMS-I.D
Audit Analysis
A grid-connected solar PV project in Rajasthan with VVB-confirmed additionality and a jurisdictional baseline, but the verification process surfaced eight material findings and eight corrective actions, primarily around PDD completeness and monitoring plan deficiencies. The project type carries inherently low permanence and leakage risk, yet the absence of verified ERR figures and a contradiction in the leakage treatment between documents leave meaningful uncertainty about the robustness of the credit claims.
Red Flags
- Eight material findings reported by Bureau Veritas, including missing measurement methods, QA/QC procedures, and calibration frequency in the monitoring plan
- PV module types in the PDD did not match Purchase Order details, raising questions about whether the as-built system matches the documented design
- Total verified ERR is not stated in the extracted record, preventing any pro-rata comparison against the 60,584 tCO2e lifetime claim
- Contradiction between the monitoring report (leakage deemed negligible) and the 2011 appendix (leakage quantified) is unresolved
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2023 | 59,879 | 0 | 59,879 | |
| Total | 59,879 | 0 | 59,879 |
Risk Indicators
VVB-confirmed
Solar PV – no reversal risk
Negligible but inconsistent across docs
Jurisdictional, reassessment timing unstated
Mentioned, FPIC/grievance not detailed
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →