Grid connected Wind Power Generation Project by PSW

CDM-6912 ↗

#844of 1935 in Renewable energy#429of 975 in India#594of 1459 in CDM (UNFCCC)#285of 806 in AMS-I.D

5.3/ 10
Integrity
5.5
Transparency
5.0
Claim Safety
5.5
Documentation
5.0

Audit Analysis

A CDM grid-connected wind project in India with a VVB-verified investment additionality test and a standard jurisdictional grid baseline, but undermined by six material findings on the investment analysis (WACC, sensitivity, data references) and unresolved contradictions between the PDD and monitoring report on baseline method and crediting period. The project delivered roughly 86% of its pro-rata ex-ante expectation, indicating conservative rather than inflated crediting, but documentation quality and transparency gaps limit confidence.

Red Flags

  • Six material findings in the validation/verification process, including WACC calculation errors, missing tariff sensitivity analysis, and unsupported input values in the investment analysis, directly undermining the robustness of the additionality claim
  • Contradiction between the PDD (project-specific baseline) and the monitoring report (jurisdictional baseline) on the baseline method, with no clear resolution documented
  • No verified ERR figure found in the extracted record; only the claimed figure of 96,635 tCO2e from the monitoring report is available, making independent cross-checking impossible

Credit Vintages

IssuedRetiredAvailable
2023
97,138097,138
Total97,138097,138

Risk Indicators

Additionality

VVB-verified but 6 material findings on investment analysis

Permanence

Avoidance project, no reversal risk

Leakage

0% justified for grid-connected wind

Baseline

Jurisdictional grid EF, but method contradicts validation re

Safeguards

Safeguards and benefit sharing mentioned, no FPIC or grievan

Double-claim

CORSIA and CCP status not stated in available documents

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-30AMS-I.D.ver.17

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents