GS11638 GS11640 RVPA-4 SPOUTS Water Purifier Programme in Africa- WPS in Uganda by AERA- VPA 14
GS-4557 ↗ · current registry ID: GS12801
#112of 1329 in Industrial#10of 163 in Uganda#228of 1801 in Gold Standard (GS)
Audit Analysis
The SPOUTS Water Purifier Programme in Uganda is a Gold Standard energy-efficiency project with VVB-verified additionality and a reasonable 5% leakage deduction, but it relies on a project-specific baseline, lacks a stated buffer pool, and shows a notable contradiction between the verification report and monitoring report on how leakage was treated. The project delivered roughly 216% of its pro-rata ex-ante expectation for the first monitoring year, suggesting a conservative baseline, though the verified ERR figure was not found in the extracted record.
Red Flags
- Leakage justification is described as 'not addressed' in the verification report (Aug 2025) but 'quantified' in the monitoring report (Sep 2025) — the VVB's own report does not confirm the 5% deduction
- Total ERR verified figure is not found in the extracted record; only the claimed figure (71,034 tCO₂e) from the monitoring report is available
- Usage monitoring method is contradictory: the verification report states 'annual survey' while the monitoring report states 'self-report'
- Three corrective actions remain open, including the requirement to obtain an expert-calculated fNRB before the first performance review
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2024 | 21,215 | 0 | 21,215 | |
| 2025 | 9,257 | 0 | 9,257 | |
| Total | 30,472 | 0 | 30,472 |
Risk Indicators
VVB-confirmed combined test
reversal not addressed
5% deduction applied but VVB report does not confirm
Project-specific baseline; reassessment not yet due
FPIC, grievance mechanism, benefit sharing documented
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →