GS1247 VPA 303 - Togo Safe Water
GS-3163 ↗ · current registry ID: GS11176
#1147of 1329 in Industrial#9of 15 in Togo#1600of 1801 in Gold Standard (GS)
Audit Analysis
The Togo Safe Water project has VVB-confirmed additionality and no reported reversal events, but suffers from significant data reliability issues including ten inter-document contradictions, no verified ERR figure, a 0% leakage deduction that contradicts an earlier 5% figure, and serious borehole capacity failures (30% and 70% reductions). The absence of a buffer pool and the unresolved open corrective actions (FAR 01–05) further weaken confidence in the project's long-term integrity and claim accuracy.
Red Flags
- No verified ERR figure is available in any document, making it impossible to confirm actual delivery against the ex-ante estimate
- Borehole AGB026 experienced a 30% capacity reduction and full breakdown (Feb 2024); borehole ASR017 had a 70% capacity reduction (Dec 2023–Apr 2024), undermining the permanence of claimed reductions
- Leakage deduction was reduced from 5% (PDD, 2023) to 0% (monitoring report, 2025) with only a 'deemed negligible' justification, contradicting the earlier quantified approach
- Lifetime ex-ante ERR is internally contradictory: 9,919 tCO₂e (PDD 2021) versus 49,595 tCO₂e (PDD 2020), a five-fold discrepancy
- No buffer pool percentage is stated in any available document, leaving reversal risk unmitigated
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2023 | 4,236 | 0 | 4,236 | |
| 2024 | 4,550 | 0 | 4,550 | |
| Total | 8,786 | 0 | 8,786 |
Risk Indicators
VVB-confirmed combined test
borehole failures
0% deduction, inconsistent justification
Project-specific, reassessed 2024
FPIC, grievance, benefit sharing
CCP/CORSIA status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →