Skip to main content
GSEnergy Efficiency - DomesticTogoGeneral Methodologyv2.1

GS1247 VPA 304 - Togo Safe Water

GS-3164 ↗ · current registry ID: GS11177

#1106of 1329 in Industrial#7of 15 in Togo#1557of 1801 in Gold Standard (GS)

4.1/ 10
Integrity
4.5
Transparency
3.5
Claim Safety
4.0
Documentation
4.5

Audit Analysis

The Togo Safe Water project (GS1247 VPA 304) has VVB-confirmed additionality and no reported reversals, but is undermined by a complete absence of a verified emissions reduction figure, a seven-fold discrepancy between claimed and PDD-stated ERR values, significant borehole capacity failures during the monitoring period, and a direct contradiction on whether FPIC was conducted. The project also lacks a stated buffer pool and relies on a project-specific baseline with a 0% leakage deduction that conflicts with the PDD's 5% figure.

Red Flags

  • No verified ERR figure exists in the extracted record; the claimed 69,437 tCO2e (monitoring report, Jul 2025) is contradicted by the PDD's 9,919 tCO2e (Jul 2021) — a roughly 7× gap that cannot be reconciled without a verified audit trail
  • Borehole AGB026 suffered a 30% capacity reduction and full breakdown (Feb 2024), and borehole ASR017 lost 70% of capacity (Dec 2023–Apr 2024), yet the project still claims full emission reductions for the monitoring period
  • FPIC status is directly contradicted: the monitoring report (Jul 2025) states FPIC was not conducted, while the validation report (Aug 2025) states it was — a fundamental safeguard inconsistency
  • Leakage deduction is 0% in the 2025 monitoring report but was 5% in the 2023 PDD; the justification shifted from 'quantified' to 'deemed negligible' without a documented re-analysis

Credit Vintages

IssuedRetiredAvailable
2023
2,80002,800
2024
4,77504,775
Total7,57507,575

Risk Indicators

Additionality

VVB-confirmed combined test

Permanence

no reversals

Leakage

0% deduction; PDD had 5%; justification shifted

Baseline

Project-specific; reassessed 2024

Safeguards

FPIC contradicted; grievance mechanism present

Double-claim

CCP and CORSIA status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-03General Methodology v2.1

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents