Audit Analysis
A Gold Standard improved cookstove sub-project in Eritrea with VVB-confirmed additionality and no reported reversals, but hampered by a long list of material findings and corrective actions, an absent buffer pool, and a project-specific baseline. The verified ERR figure is missing from the extracted record, limiting the ability to confirm over- or under-delivery. Overall a moderate-quality project with meaningful compliance gaps that are being addressed.
Red Flags
- Eight compliance-level findings (CL#01–CL#08) and five corrective action requests (CAR#01–CAR#05) were raised across verification cycles, with three forward action requests still open as of the July 2024 verification report
- The verified ERR figure is not present in the extracted record, preventing a direct comparison against the 4,108 tCO₂e claimed for the 2023–2024 monitoring period
- The FNRB method is contradictory: the 2023 PDD describes a local field measurement while the 2024 verification report records a national default value of 97
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2016 | 274 | 274 | 0 | |
| 2017 | 10,000 | 10,000 | 0 | |
| 2018 | 10,000 | 10,000 | 0 | |
| 2019 | 7,238 | 7,238 | 0 | |
| 2020 | 3,597 | 3,428 | 169 | |
| 2021 | 4,284 | 2,423 | 1,861 | |
| 2022 | 3,875 | 1,024 | 2,851 | |
| 2023 | 2,161 | 0 | 2,161 | |
| Total | 41,429 | 34,387 | 7,042 |
Risk Indicators
VVB-confirmed combined test
no reversals reported
Deemed negligible, 0% deduction
Project-specific, reassessed 2024
FPIC, grievance mechanism, safeguards documented
CCP and CORSIA status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →