GS5047 VPA29 African Improved Cookstoves and Clean Water Programme: Nyagatare Safe Water Project IX
GS-1581 ↗ · current registry ID: GS7398
#909of 1329 in Industrial#79of 139 in Rwanda#1327of 1801 in Gold Standard (GS)
Audit Analysis
The Nyagatare Safe Water Project IX is a Gold Standard energy-efficiency project in Rwanda with VVB-confirmed additionality and an established methodology, but the verification report reveals significant MRV weaknesses including unverified borehole GPS locations, a 9% increase in downtime, 12 boreholes removed during the period, and multiple corrective actions still outstanding. The 0% leakage deduction is justified as negligible but contradicts an earlier 'quantified' treatment, and the project-specific baseline lacks a documented reassessment date. Overall, the project shows moderate integrity with notable data-reliability concerns that temper confidence in the claimed emission reductions.
Red Flags
- Average borehole downtime increased from 1.2% in MP3 to 9.0% in MP4 due to supply-chain disruptions, yet no corresponding ER adjustment is documented
- 12 boreholes were removed from the project database during the 2023 monitoring period, raising over-crediting risk if ERs were calculated before removal
- Borehole GPS locations could not be verified from provided data; physical verification or updated satellite imagery is still pending as a corrective action
- Potential double counting of users in overlapping borehole radii was addressed only by capping at 300 users, a methodological shortcut rather than a rigorous spatial analysis
- Multiple corrective actions remain open (GPS recollection, physical borehole verification, survey methodology fixes), indicating the MRV system was not fully robust at verification time
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2019 | 3,835 | 3,835 | 0 | |
| 2020 | 4,683 | 4,677 | 6 | |
| 2021 | 11,192 | 11,137 | 55 | |
| 2022 | 9,692 | 9,499 | 193 | |
| 2023 | 3,326 | 0 | 3,326 | |
| 2024 | 1,894 | 0 | 1,894 | |
| Total | 34,622 | 29,148 | 5,474 |
Risk Indicators
VVB-confirmed combined test
mixed evidence / unresolved risk
0% deemed negligible; contradicts earlier quantified treatment
Project-specific; no reassessment date found
FPIC and grievance present but inconsistently documented
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →