Guertu River Cascade Stage III 13.5MW Hydropower Project
#1027of 1935 in Renewable energy#569of 1084 in China#762of 1459 in CDM (UNFCCC)#329of 806 in AMS-I.D
Audit Analysis
A 13.5 MW run-of-river hydropower project in China verified under CDM AMS-I.D. with additionality confirmed via an investment test by TÜV NORD CERT. The project shows a significant under-delivery relative to its ex-ante estimate, which provides a conservative safety margin, but the reliance on a 2006 grid emission factor, absence of a buffer pool, and contradictory leakage characterizations across monitoring reports introduce moderate integrity and claim-safety concerns.
Red Flags
- Grid emission factor of 0.8712 tCO2/MWh is drawn from 2006 data, making the baseline potentially outdated and inflating claimed reductions relative to current grid intensity.
- Twenty material findings at validation included errors in the IRR calculation (incorrect tax rate, VAT misclassified as expense, construction-period inconsistency), raising questions about the robustness of the additionality investment test.
- No buffer pool or permanence mechanism is documented, and no reversal-event data is available in the extracted record.
- Leakage justification is contradictory: the 2016 monitoring report states it was 'deemed negligible' while the 2022 monitoring report records it as 'not addressed.'
- Thirty-seven corrective actions were required at validation, indicating substantial initial documentation and calculation weaknesses.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2012 | 32,932 | 0 | 32,932 | |
| 2013 | 32,900 | 0 | 32,900 | |
| 2017 | 146,031 | 0 | 146,031 | |
| 2023 | 67,942 | 0 | 67,942 | |
| Total | 279,805 | 0 | 279,805 |
Risk Indicators
VVB-confirmed investment test
low inherent risk
0% deduction; justification contradictory across reports
2006 grid EF; method label inconsistent across docs
Safeguards mentioned; FPIC and grievance mechanism not docum
CORSIA and CCP status not stated in available records
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →