CDMWindChinaACM0002

Guangdong Leiling Wind Power Project

CDM-4747 ↗

#551of 1935 in Renewable energy#252of 1084 in China#370of 1459 in CDM (UNFCCC)#420of 1287 in ACM0002

5.7/ 10
Integrity
6.5
Transparency
5.5
Claim Safety
4.0
Documentation
7.0

Audit Analysis

The Guangdong Leiling Wind Power Project is a CDM-registered wind avoidance project validated by DNV with a confirmed combined additionality test and a jurisdictional baseline. However, a significant discrepancy between the ex-ante emissions reduction estimate (82,096 tCO₂ over 7 years) and the first monitoring period claim (55,665 tCO₂ over ~11 months) raises serious over-crediting concerns, as the claimed figure is roughly five times the pro-rata expectation. Several key data points (verified ERR, FN/RB method, CORSIA/CCP status) are absent from the extracted record, limiting full assessment.

Red Flags

  • The monitoring report claims 55,665 tCO₂ for an 11-month period, while the validation report's ex-ante estimate is 82,096 tCO₂ over the full 7-year crediting period — the claimed figure is approximately 5.2× the pro-rata expectation (~10,750 tCO₂), indicating a potential over-crediting risk.
  • Baseline method is described as 'jurisdictional' in the monitoring report but as 'project-specific' in the validation report, creating ambiguity about the actual baseline construction.
  • Total verified ERR for the monitoring period is not stated in the extracted record, preventing independent verification of the claimed figure.
  • Leakage justification is inconsistent across documents: 'deemed negligible' in the monitoring report versus 'quantified' in an unidentified source document.

Credit Vintages

IssuedRetiredAvailable
2012
55,665055,665
Total55,665055,665

Risk Indicators

Additionality

Combined test confirmed by DNV

Permanence

Avoidance project, no reversal events

Leakage

0% deduction, thin justification, doc conflict

Baseline

Jurisdictional vs project-specific conflict

Safeguards

Mentioned but FPIC/grievance not detailed

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-30ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents