Guizhou Yanhe Guanba 18.9MW Hydropower Station Project
#437of 1935 in Renewable energy#171of 1084 in China#283of 1459 in CDM (UNFCCC)#325of 1287 in ACM0002
Audit Analysis
A standard CDM small-hydro avoidance project (18.9 MW) with a jurisdictional grid-emission-factor baseline and a VVB-confirmed investment additionality test. The core design is sound and leakage is reasonably justified as negligible, but the absence of any verified monitoring data, monitoring period, or usage-tracking method creates a significant transparency gap that prevents independent confirmation of actual credit delivery.
Red Flags
- No verified ERR figures or monitoring period found in any available document, making it impossible to confirm whether the 326,886 tCO₂e lifetime claim was actually delivered
- Additionality test type is described as 'investment' in the validation report but 'combined' in the PDD, creating ambiguity about the full scope of the additionality assessment
- No monitoring reports appear in the evidence document set, leaving the project's operational performance unverified
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed investment test
Avoidance project, no reversal risk
0% justified as negligible
Jurisdictional grid EF baseline
Mentioned but FPIC/grievance not detailed
CORSIA and CCP status unstated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →