Gulman Group Solar Power Plant Bundle

ICR-174 ↗

#685of 1935 in Renewable energy#9of 75 in TR#14of 154 in Intl. Carbon Registry (ICR)#241of 806 in AMS-I.D

5.5/ 10
Integrity
6.5
Transparency
4.5
Claim Safety
5.5
Documentation
5.0

Audit Analysis

A solar power avoidance project in Turkey with a jurisdictional baseline and VVB-confirmed combined additionality test, but hampered by numerous documentation deficiencies, contradictory leakage characterizations across reports, and a lack of verified emission reduction data to confirm the claimed figures. The fundamental project design is sound for a renewable energy avoidance credit, yet the verification record shows material gaps that limit confidence in the reported numbers.

Red Flags

  • Twelve material findings in the validation report, including substantive issues such as unverified meter serial numbers for some plants, questioned PM2.5/PM10 attribution, and incomplete investment analysis
  • Leakage justification is contradictory: the monitoring report states it was 'quantified' while the validation report (2025-06-25) characterizes it as 'deemed negligible', with a 0% deduction in both cases
  • Total ERR claimed appears as both 12,446 and 124,460 in two validation reports dated 2025-07-17 and 2025-06-25 respectively, creating ambiguity about whether the figure is annual or lifetime
  • No verified ERR figure is available in the extracted record, preventing any pro-rata delivery check against the ex-ante estimate
  • Three corrective actions remain open, including alignment with ICR program version 6 and completion of the environmental and socioeconomic safeguards tool

Credit Vintages

IssuedRetiredAvailable
2017
3,71203,712
2018
12,310012,310
2019
13,470013,470
2020
13,828013,828
2021
12,916012,916
2022
12,916012,916
2023
12,916012,916
2024
12,916012,916
2025
12,916012,916
2026
12,916012,916
2027
3,64403,644
Total124,4600124,460

Risk Indicators

Additionality

VVB-confirmed combined test

Permanence

Avoidance project, no reversal risk

Leakage

0% deduction, contradictory justification

Baseline

Jurisdictional, reassessment timing unstated

Safeguards

FPIC, grievance mechanism, safeguards documented

Double-claim

CORSIA and CCP status both unstated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-08AMS-I.D.

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents