Guodian Juxian Wind Power Phase I Project
#1250of 1935 in Renewable energy#735of 1084 in China#976of 1459 in CDM (UNFCCC)#969of 1287 in ACM0002
Audit Analysis
A CDM wind power project in China with a verified combined additionality test and a jurisdictional grid-emission-factor baseline, but severely limited by the complete absence of monitoring reports and verified emission reduction figures. A seven-fold discrepancy between the PDD and validation report on total claimed credits raises material data-reliability concerns. The project's 2012–2019 crediting period has lapsed, and no post-validation evidence is available in the extracted record.
Red Flags
- Seven-fold discrepancy in total claimed ERR: the PDD (May 2012) states 584,563 tCO₂e while the validation report (May 2012) states 83,509 tCO₂e; the VVB-validated figure is privileged but the gap undermines confidence in the credit quantity.
- No monitoring reports, verified ERR, or monitoring period data are present in the extracted record, making it impossible to confirm actual delivery against the validated baseline.
- Eleven material findings (6 CARs, 5 CLs) were raised during validation, including missing Letters of Agreement, incomplete additionality documentation, and a sensitivity-analysis error; although the corrective-actions list is empty, the volume of findings signals a weak initial submission.
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed combined test
Avoidance project, no reversal risk
0% deemed negligible, appropriate for wind
Jurisdictional grid EF (2011)
Mentioned but FPIC/grievance not detailed
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →