Guodian Liaocheng Biomass Power Project

CDM-2963 ↗

#93of 352 in Biomass#561of 1084 in China#754of 1459 in CDM (UNFCCC)#14of 81 in ACM0006

5.1/ 10
Integrity
5.5
Transparency
4.5
Claim Safety
5.0
Documentation
5.5

Audit Analysis

The Guodian Liaocheng Biomass Power Project is a CDM biomass-to-electricity project with VVB-confirmed additionality and a standard grid-displacement baseline, but it is undermined by four cross-document contradictions (baseline method, leakage justification, ERR magnitude, and crediting period dates), a 0% leakage deduction with inconsistent rationale, and the absence of any verified ERR figure. The project's permanence risk is inherently low for a power-generation credit, yet the data-quality gaps and contradictory records limit confidence in the underlying claims.

Red Flags

  • Four contradictions between the validation report (2010) and the monitoring report (2011/2013) on baseline method, leakage justification, total ERR, and crediting-period dates indicate inconsistent project documentation
  • Leakage deduction is 0% with the justification shifting from 'deemed negligible' (validation report) to 'quantified' (monitoring report) without a clear quantified figure in the extracted record
  • Total ERR verified is not stated in any available document, leaving no independently confirmed emission-reduction figure
  • Grid emission factor is from 2009 and no updated or reassessed baseline value is found in the extracted record

Credit Vintages

IssuedRetiredAvailable
2013
239,3380239,338
Total239,3380239,338

Risk Indicators

Additionality

Combined test confirmed by DNV

Permanence

Power-generation credit, no reversal risk

Leakage

0% deduction, inconsistent justification

Baseline

Project-specific, method contradicts validation report

Safeguards

Safeguards mentioned, benefit sharing described, no FPIC or

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-30ACM0006

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents