Guodian Penglai Hushan Phase I Wind Farm Project
#1251of 1935 in Renewable energy#737of 1084 in China#978of 1459 in CDM (UNFCCC)#971of 1287 in ACM0002
Audit Analysis
A CDM wind project with a solid VVB-confirmed additionality assessment and a standard jurisdictional grid baseline, but significant gaps in leakage treatment, absence of any monitoring or verification data, and a 10× discrepancy in the claimed emission reduction figure between the PDD and the validation report. The project's integrity is moderate, while transparency and claim safety are weakened by the lack of post-validation evidence and unresolved data inconsistencies.
Red Flags
- The PDD states a total ERR of 827,900 tCO₂e while the validation report (the authoritative VVB document) records 82,790 tCO₂e — a tenfold discrepancy that undermines confidence in the project's quantification
- Leakage was assigned a 0% deduction and the validation report records the justification as 'not addressed', while the PDD merely states it was 'deemed negligible' — no substantive leakage analysis is documented
- No monitoring reports, verification reports, or verified ERR figures are available for the full 2012–2022 crediting period, leaving the project's actual performance entirely unverified
- Six material findings were raised during validation (including inconsistent O&M costs, loan interest figures, and unsupported common-practice evidence), all of which were resolved before the validation report was issued, but the volume of corrections signals a weak initial PDD
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed combined test
mixed evidence / unresolved risk
0% deduction, justification 'not addressed' per validation r
Jurisdictional grid EF, standard for ACM0002 wind
Safeguards and benefit sharing mentioned; FPIC and grievance
CCP and CORSIA status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →