Guodian Shaoyang Xinning Fengyudian Wind Power Project
#848of 1935 in Renewable energy#436of 1084 in China#599of 1459 in CDM (UNFCCC)#661of 1287 in ACM0002
Audit Analysis
A CDM wind power project in China with a jurisdictional grid-emission-factor baseline and VVB-confirmed combined additionality test, but limited monitoring data, a significant discrepancy between the PDD and validation report on total emissions reductions, and only partial safeguards documentation. The project is methodologically sound for its sector but lacks the depth of verified performance data and stakeholder-protection detail expected of a high-quality credit.
Red Flags
- Total ERR differs by a factor of ~7 between the PDD (590,499 tCO₂e) and the validation report (84,357 tCO₂e); the PDD figure likely covers the full 7-year crediting period while the validation report may reflect a single-year estimate, but this is not explicitly reconciled in the available documents.
- Two corrective actions (CARs) were raised by the VVB regarding missing Letters of Agreement and incomplete monitoring information for electricity export/import, indicating the PDD was not fully complete at validation.
- No monitoring reports, verified ERR figures, or post-validation performance data were found in the extracted record, leaving actual delivery unconfirmed.
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed combined test
Avoidance project, low reversal risk
0% with negligible justification
Jurisdictional grid EF (2009)
Mentioned but not detailed; no FPIC or grievance mechanism f
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →