Guodian Weifang Binhai Wind Farm Phase I Project
#1491of 1935 in Renewable energy#929of 1084 in China#1244of 1459 in CDM (UNFCCC)#1136of 1287 in ACM0002
Audit Analysis
A CDM wind project with a confirmed additionality test and jurisdictional baseline, but undermined by 11 material findings in the validation report, an unaddressed leakage assessment, and a seven-fold discrepancy in claimed emissions reductions between the PDD and the validation report. No monitoring reports or verified performance data are available, making it impossible to confirm actual delivery against the claimed 96,316 tCO₂e.
Red Flags
- Seven-fold discrepancy in total ERR: the PDD claims 674,212 tCO₂e while the validation report (the authoritative VVB document) records 96,316 tCO₂e — a 7× gap that cannot be reconciled from available documents
- Leakage was not addressed in the validation report (stated as 'not addressed'), while the PDD merely deemed it negligible without quantification — a 0% deduction with no substantive justification
- 11 material findings (CARs) in the validation report, including missing PDD revision history, unclear monitoring plan for shared meters, and methodology version inconsistencies
- No monitoring reports, verified ERR, or post-validation documents are available in the extracted record, leaving actual performance entirely unverified
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed combined test
Avoidance project, no reversal risk
0% deduction, not addressed in VVB report
Jurisdictional grid EF, 2011
Mentioned but no FPIC or grievance mechanism documented
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →