Guohua Shangyi Kangleng Phase I Wind Farm Project
#1257of 1935 in Renewable energy#744of 1084 in China#985of 1459 in CDM (UNFCCC)#977of 1287 in ACM0002
Audit Analysis
A CDM wind farm project with solid additionality (VVB-confirmed combined test) and a standard jurisdictional grid baseline, but the available record is limited to validation-stage documents with no monitoring or verification reports. A significant seven-fold discrepancy in the claimed emission reduction between the PDD and the validation report raises data-reliability concerns, and the absence of any post-validation evidence limits confidence in actual delivery.
Red Flags
- Seven-fold discrepancy in claimed lifetime ERR: the PDD (2012-05-10) states 753,151 tCO2e while the validation report (2012-05-21) states 107,593 tCO2e — a factor-of-7 gap that is unexplained in the extracted record
- No monitoring reports, verification reports, or verified ERR figures are present in the available documentation; the project's actual credit delivery cannot be confirmed
- No FNRB value, usage monitoring method, or CORSIA/CCP eligibility status is stated in any available document
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed combined test
Avoidance project, no reversal risk
0% with negligible justification, appropriate for wind
Jurisdictional grid EF, standard for CDM wind
Safeguards and benefit sharing mentioned; no FPIC or grievan
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →